1. When the ready mix plant equipment has worked for two to four hours, the operator should inject about 10ml oil into the butter mouth of the host.

2. Steel rope of hopper needs to be lubricated by grease or motor oil to keep it wet, grease is also required inside and outside the rail.

3. Gear of the host and the concrete batching machine should be lubricated by grease.

4. When the new ready mix concrete plant works for 200 hours, each reduces should change the lubrication oil as required, later, change it after 2000 hours working.

Meanwhile, the cleaning of ready mix dry plants is also essential. The client can clean up the mixing drum, but usually, ignore clean the cement feed port. If it is not cleaned for a long time, cement cannot enter the concrete mixer smoothly.